Project Executive Summary


National Highways Authority of India

(Ministry of Road Transport & Highways)
Government of India

 

Four Laning of End ofPandoh bypass to Takoli section ofNH-21from km 221.305 to km 242.000 in the State of Himachal Pradeshunder NHDP
Phase IVB-Package-11 to be executed on HybridAnnuity Mode

CONCESSION AGREEMENT

Between

National Highways Authority of India

G- 5&6, Sector- 10, Dwarka, New Delhi- 110 075

and

M/s Shapoorji Pallonji PandohTakoli Highway PrivateLimited

Shapoorji Pallonji Centre, 41/44, Minoo Desai Marg, Colaba, Mumbai, Mumbai City, Maharashtra – 4000005.

High way

  • Stretch-1 Km. 216+290 to 218+507 =2217m
  • Stretch-2 Km. 220+560 to 221+010 = 450m
  • Stretch-3 Km. 221+375 to 221+870 = 495m
  • Stretch-4 Km. 223+900 to 224+070 = 170m
  • Stretch-5 Km. 225+855 to 227+855 =2005m
  • Stretch-6 Km. 227+860 to 230+290 =2430m
  • Stretch-7 Km. 233+140 to 234.507 =1367m
  • Major/ Minor Junctions

Tunnel:

  • T4-01 Twin Tube of two lane 218+507 – 220+560 =2053m
  • T4-02 Twin Tube of two lane 221+010 – 221+375 = 365m
  • T4-03 Twin Tube of two lane 221+870 – 223+900 =2030m
  • T4-04 Twin Tube of two lane 224+070 – 225+855 =1785m
  • T2-01 Single Tube of two lane 226+365 – 227+860 =1495m
  • T2-02 Single Tube of two lane 230+290 – 233+140 =2850m
  • Connector – C1 231+000 LHS – 233+300 RHS =725m
  • Connector – C2 231+700 LHS – 233+800 RHS =430m
  • Connector – C3 232+400 LHS – 234+600 RHS =435m
  • Rehabilitation of Existing Tunnel 232+110 – 234+925=2815m

Elevated Structure:@Km 226.110 =17x30=510m
Minor Bridges

LHS Side

  • Minor Bridge @ Km 220.722 PSC 1x40m
  • Minor Bridge @ Km 221.410 PSC 1x30m
  • Minor Bridge @ Km 224.010 PSC 1x30m
  • Minor Bridge @ Km 228.855 PSC 1x30m
  • Minor Bridge @ Km 230.241 RCC-T 1x20m
  • Minor Bridge @ Km 233.582 PS-SITU 1x20m

Project Facilities

  • Road Side Furniture
  • PedestrianFacilities
  • Tree Plantation
  • Bus-bays and Bus Shelter
  • Others

Project Milestones:

  • PM-I achieve 35% physical progress 17-Feb-19*
  • PM-II achieve 35% physical progress 24-Sep-19*
  • PM-III achieve 75% physical progress 23-Nov-20*
  • Scheduled Completion Date 23-Sep-21*