Project Executive Summary
National Highways Authority of India
(Ministry of Road Transport & Highways)
Government of India
Four Laning of End ofPandoh bypass to Takoli section ofNH-21from km 221.305 to km 242.000 in the State of Himachal Pradeshunder NHDP
Phase IVB-Package-11 to be executed on HybridAnnuity Mode
CONCESSION AGREEMENT
Between
National Highways Authority of India
G- 5&6, Sector- 10, Dwarka, New Delhi- 110 075
and
M/s Shapoorji Pallonji PandohTakoli Highway PrivateLimited
Shapoorji Pallonji Centre, 41/44, Minoo Desai Marg, Colaba, Mumbai, Mumbai City, Maharashtra – 4000005.
High way
- Stretch-1 Km. 216+290 to 218+507 =2217m
- Stretch-2 Km. 220+560 to 221+010 = 450m
- Stretch-3 Km. 221+375 to 221+870 = 495m
- Stretch-4 Km. 223+900 to 224+070 = 170m
- Stretch-5 Km. 225+855 to 227+855 =2005m
- Stretch-6 Km. 227+860 to 230+290 =2430m
- Stretch-7 Km. 233+140 to 234.507 =1367m
- Major/ Minor Junctions
Tunnel:
- T4-01 Twin Tube of two lane 218+507 – 220+560 =2053m
- T4-02 Twin Tube of two lane 221+010 – 221+375 = 365m
- T4-03 Twin Tube of two lane 221+870 – 223+900 =2030m
- T4-04 Twin Tube of two lane 224+070 – 225+855 =1785m
- T2-01 Single Tube of two lane 226+365 – 227+860 =1495m
- T2-02 Single Tube of two lane 230+290 – 233+140 =2850m
- Connector – C1 231+000 LHS – 233+300 RHS =725m
- Connector – C2 231+700 LHS – 233+800 RHS =430m
- Connector – C3 232+400 LHS – 234+600 RHS =435m
- Rehabilitation of Existing Tunnel 232+110 – 234+925=2815m
Elevated Structure:@Km 226.110 =17x30=510m
Minor Bridges
LHS Side
- Minor Bridge @ Km 220.722 PSC 1x40m
- Minor Bridge @ Km 221.410 PSC 1x30m
- Minor Bridge @ Km 224.010 PSC 1x30m
- Minor Bridge @ Km 228.855 PSC 1x30m
- Minor Bridge @ Km 230.241 RCC-T 1x20m
- Minor Bridge @ Km 233.582 PS-SITU 1x20m
Project Facilities
- Road Side Furniture
- PedestrianFacilities
- Tree Plantation
- Bus-bays and Bus Shelter
- Others
Project Milestones:
- PM-I achieve 35% physical progress 17-Feb-19*
- PM-II achieve 35% physical progress 24-Sep-19*
- PM-III achieve 75% physical progress 23-Nov-20*
- Scheduled Completion Date 23-Sep-21*